Zelestra and EDP strengthened their collaboration in Spain with two new hybrid PPAs that will incorporate 462 MWh of battery storage to 181 MWdc of solar capacity.
The agreements pertain to the Pedroso project in Seville and the Valkyria project in Castilla-La Mancha. In both cases, additional measures will be added BESS systems to existing photovoltaic installations, which will allow part of the solar generation to be stored and its delivery shifted to other times of the day.
Zelestra will own the projects while EDP will act as the energy buyer through new long-term power purchase agreements.
The hybrid PPAs will incorporate four-hour batteries.
In Pedroso, Zelestra will combine a 31 MWdc solar plant with a 25 MW BESS system and a 100 MWh battery storage capacity. Valkyria, meanwhile, will have 150 MWdc of photovoltaic generation and a 90.45 MW battery storage system with a 362 MWh capacity.
The two systems will have approximately four hours of storage capacity. Together, they will provide the additional 462 MWh included in the new hybrid PPAs.
This configuration allows the electricity produced during peak solar generation hours to be harnessed and stored for later use. In this way, batteries can increase the flexibility of power plants and reduce their reliance on production tied solely to hours of sunlight.
Zelestra and EDP exceed 1 GWh of contracted storage
The Pedroso and Valkyria agreements bring to four the number of solar energy and storage projects included in the collaboration between Zelestra and EDP in Spain.
In 2025, the companies agreed a PPA for the Trujillo project in Extremadura, which combines 170 MWdc of solar capacity with 400 MWh of battery storage.
Subsequently, in 2026, both companies expanded their collaboration through Pizarroso, a 50 MW solar plant in Cáceres where a 160 MWh BESS system will be incorporated.
With Pedroso and Valkyria, the storage capacity linked to the four agreements reaches approximately 1,022 MWh.
Unlike Trujillo, developed as a new solar project with storage, Pedroso, Valkyria and Pizarroso take advantage of photovoltaic plants existing ones to incorporate batteries.
Batteries increase the flexibility of solar plants
Hybridizing operational facilities allows for the addition of storage using existing infrastructure such as land, generation, and grid access.
In addition, the model makes it easier for some of the renewable electricity produced during the day to be shifted to the late afternoon, evening, or other periods of higher demand.
For independent power producers, this capacity opens up new commercial opportunities within PPAs. solar generation it is no longer strictly linked to the moment it occurs and can be better adapted to the buyer’s consumption profile.
Zelestra has transferred to Europe some of the experience gained in markets such as Chile, where contracts combining renewable generation and storage have a longer track record.
Likewise, the company is expanding this type of commercial structure in other European markets through hybrid PPAs and long-term storage contracts.
Spain gains energy storage capacity
The new operation also reinforces the role of BESS systems within Spanish renewable growth.
Jaime Burguete, head of Zelestra in Spain, pointed out that the four joint projects demonstrate the viability of energy storage in the country and predicted that this segment will have a growing importance in the coming years.
For its part, EDP seeks to use the combination of renewable generation and storage to provide a more flexible electricity supply and make better use of the energy produced by renewables solar installations.
With the new agreements, Zelestra and EDP are expanding a strategy that links long-term supply contracts with large-scale batteries, a formula that can facilitate greater integration of solar energy within the Spanish electricity system.
Sources: Energy Storage News