Yinson and Eni will expand the gas processing and export capacity of the FPSO John Agyekum Kufuor (JAK) the project, which operates off the coast of Ghana, includes the installation of new compression equipment and several modifications to the vessel’s superstructure, the intervention is part of a contractual modification linked to the development of a project. non-associated gas (NAG) Once the new facilities are incorporated, the FPSO’s gas export capacity will increase from approximately 210-220 million standard cubic feet per day (MMscf/d) to 355 MMscf/d the agreement will also extend the firm lease period of the unit by four years, which will remain under contract until 2036 both the expansion and the incremental daily rate associated with the project will add approximately US$600 million to Yinson Production’s firm portfolio of contracts.
Yinson and Eni will increase gas compression of the FPSO
One of the most important technical components of the project will be the incorporation of new capacity gas compression this system will compensate for the anticipated reduction in reservoir pressure and maintain larger volumes of gas available for export. Additionally, Yinson Production will make modifications to the processing plant ortopsideof the FPSO JAK. These modifications will allow for increased onboard gas handling and processing capacity before shipment from the offshore facilities.
The program includes the manufacture and integration of two main modules, the MG2 it will be equipped with two compressors powered by gas turbines, while the MC4 it will function as an auxiliary treatment module to manage the increased volume. Engineering, procurement, and manufacturing activities must be carried out under the safety and quality standards applicable to offshore installations. According to Yinson Production, this approach will preserve operational continuity and the integrity of the asset while the modifications are implemented.
The FPSO John Agyekum Kufuor will operate under contract until 2036
The completion of the NAG project is scheduled for first quarter of 2028 from that moment on, Yinson Production will begin to receive the agreed incremental daily fee, which will continue until 2036, the project thus combines a physical expansion of the processing infrastructure with an extension of the contractual life of the FPSO John Agyekum Kufuor. The unit belongs to a joint venture led by Yinson Production, which holds a controlling stake in 74 % the remaining 26% is held by a Japanese consortium made up of Sumitomo Corporation, Kawasaki Kisen Kaisha, JGC Holdings and Development Bank of Japan.
Increased gas supply for Ghana
For Ghana, the increased capacity of the FPSO is directly linked to domestic gas supply and strengthened energy security. The modifications will allow for the utilization of larger production volumes even as natural reservoir pressure decreases. Flemming Guiducci Grønnegaard, CEO of Yinson Production, noted that the increased export capacity will contribute to strengthening the offshore energy infrastructure and meeting Ghana’s domestic needs. The project also aims to extend the field’s economic life through facilities capable of adapting to new pressure conditions, with a planned capacity of 355 MMscf/d the FPSO JAK will increase by about 60 % its export capacity relative to the upper end of its current range.
Source: Offshore Energy
Photo: Shutterstock