Valeura Energy has begun offshore installation work for the redevelopment of Wassana site located in the G10/48 block of the Gulf of Thailand, operations began approximately two months ahead of schedule, which will accelerate the commissioning of a new central processing platform (CPP).
The Canadian company confirmed the start of offshore activities on October 9, after completing in September the commercial agreements and contractual adjustments necessary to move the project forward.
Wassana’s new platform is two months ahead
The redevelopment project includes the installation of a central processing platform (CPP) this will allow for an increase in oil production capacity at Wassana. This infrastructure will progressively take over the operations currently carried out by the Ingenium Mobile Offshore Production Unit (MOPU).
Valeura Energy made the final investment decision in 2025, with the aim of expanding the field’s processing capacity and utilizing larger volumes of crude oil.
The Ingenium unit is scheduled to be decommissioned by the end of 2027, therefore, the addition of the new platform will be essential to ensure the field’s operational continuity and facilitate the development of new wells.
Valeura expects to produce an additional 430,000 barrels in 2027
The acceleration of the works could also translate into an increase in production during 2027, according to estimates from Valeura Energy the new platform would achieve a stable rate of close to 7,500 barrels of oil per day.
By anticipating its launch by approximately two months, the company estimates that it could obtain an additional 430,000 barrels in 2027, compared to the initially established schedule.
This increase is due to the possibility of starting production earlier than planned and will depend on the performance of the facilities once they are operational.
The Shelf Enterprise platform will support drilling
Alongside the offshore installation work, Valeura Energy is preparing a new drilling campaign at its assets in the Gulf of Thailand. The company informed its contractor that the lease agreement for the Shelf Enterprise drilling rig will begin on November 1, 2026.
In the first stage, the team will operate in the Nong Yao field, where new wells will be drilled taking advantage of the additional slots available on the Nong Yao A platform.
Subsequently, Shelf Enterprise will participate in the drilling activities related to Wassana, in this way, Valeura seeks to coordinate the installation of the new infrastructure with the work necessary to incorporate production into the field.
Wassana could incorporate new satellite fields
The new central processing platform was also designed to facilitate future connections with satellite production facilities, which would allow the exploitation of oil resources located north and south of Wassana.
Furthermore, recent mapping studies identified potential additional oil volumes in the southern sector of the field. Based on these results, Valeura Energy is evaluating further exploratory drilling to determine the potential of these resources.
However, these opportunities are still in the evaluation phase and their development will depend on the results of exploratory work and future investment decisions.
With the early start of offshore work, Valeura Energy is moving towards a new stage of production at Wassana. The priority will be to complete the installation of the central processing platform and prepare it to begin operations in 2027.