Valaris has secured approximately $600 million in new contracts and extensions since its last fleet update, published in August 2016. These agreements bring its total backlog of contracted orders to about $4.8 billion, up from $4.6 billion as of August 5, the company announced on November 2.
The awards include work for drillships, jack-up platforms and offshore drilling services, with operations planned in the Americas, Europe, Asia, Africa and Middle East among the most relevant agreements are those signed with BP, PETRONAS and Aramco, in addition to new drilling campaigns and contract extensions for different units of its fleet.
Valaris expands its offshore drilling contracts in various regions
Among the new awards, the drilling vessel VALARIS DS-18 secured a contract to carry out a two-well exploration campaign with PETRONAS Suriname Exploration & Production, off the coast of Suriname. Operations are planned for the fourth quarter of 2026 and will last up to seven months. The agreement stems from a previously announced award letter. Its value does not include additional services that may be billed separately or compensation related to the mobilization and demobilization of the unit.
In another agreement, the company DS-12 vessel obtained a contract extension to drill a well with BP Exploration Delta, off the coast of Egypt. Work will begin in late 2027 or early 2028 and will allow the current program to continue. The extension adds 60 days of operations and represents approximately $25 million more to Valaris’s order book.
New contracts for self-elevating platforms
The fleet update also includes several awards for jack-up platforms in Australia and the North Sea. In Australia, the VALARIS 107 platform obtained a contract to drill a well with Emperor Energy. The start of operations is planned for the second quarter of 2027, with a minimum duration of 30 days and a daily rate of $165,000.
This same unit secured a second offshore contract in the country, with an approximate duration of 300 days. The agreement will add approximately $50 million to the order book, not including mobilization and demobilization compensation. It also includes additional options and will begin once the platform completes its current commitments.
Meanwhile, the VALARIS 106 obtained a contract extension to drill a well with BP Indonesia, the work is expected to begin in the fourth quarter of 2028 and will last approximately 90 days. This award will contribute about $10 million to outstanding contracted revenue, while three other options for additional wells remain available.
In the North Sea, Valaris it secured a contract to perform well plugging and abandonment work, with an estimated duration of 341 days and an approximate value of $41.5 million. The operations will take place in the southern sector of the North Sea and can be carried out with any of the suitable platforms available in the company’s regional fleet. The start is planned within a window extending to December 2030. The agreement also includes an additional 19-day option to work on a well.
Additionally, the company in Norway platform secured a contract extension with Ithaca Energy for operations in the British sector of the North Sea. Work will commence during the second quarter of 2027 and will last approximately 200 days. This extension will add around $27 million to the order book and includes additional options for a total of 163 days.
Valaris 122 expands its operations in the North Sea
Another unit expanding its operations is the VALARIS 122 platform, which secured two contract extensions with INEOS to conduct operations in the Danish and British sectors of the North Sea. The first campaign will take place in Denmark, scheduled to begin in February 2027 and last 126 days. The contract establishes a daily rate of $115,000.
Subsequently, the platform will conduct a second 158-day campaign in the British sector, scheduled to begin in July 2027. In this case, the daily rate will be $125,000. The agreement also includes additional options totaling 541 days. Furthermore, a modification to the previously announced contract for the VALARIS 72 platform with Eni, in the East Irish Sea, will allow approximately eight and a half months of work to be transferred to the VALARIS 121.
This latest unit is scheduled to begin operations in November 2026, the change brings forward the planned completion date of the VALARIS 72 program from September to March 2027 and adds approximately $17 million to the order backlog.
The VALARIS 248 platform also secured a 61-day extension with Seatrium to provide hosting and support services to an offshore wind project in the British sector of the North Sea, work began in October 2026 and added more than five million dollars to the order book.
BP provides one of the most valuable contracts for Valaris
In the area of fixed-platform drilling services, the company secured a three-year contract with BP to support operations at the Mad Dog and Thunder Horse facilities, located in the Gulf of America. The agreement will take effect in January 2027 and will allow for the direct continuation of the contract that both companies currently hold. Its addition represents approximately $290 million for the company order backlog. Due to its economic value, this award ranks among the most important contracts included in the company’s latest fleet upgrade.
ARO Drilling expands its agreements with Aramco
In the Middle East, ARO Drilling, the joint venture between Valaris and Aramco, secured three-year extensions with Aramco for five of its rigs, these extensions, which took effect in October 2026, guarantee the continued operation of these drilling units in the region. The company also noted that all of its rigs and ARO Drilling units operating in the Middle East remain under contract, reflecting the high level of activity of its fleet in one of the world’s leading offshore drilling markets.
Changes to the Valaris fleet
The update also reflects changes in the composition of the company’s assets; the VALARIS MS-1 semi-submersible platform was sold for recycling, while the company canceled the previously announced sale of the VALARIS 111 jack-up platform, which was also destined for that process.
Subsequently, the company found another buyer for this unit, which will be converted into a mobile offshore production unit (MOPU). With these new contracts and the changes made to its fleet, the company contracted order backlog stands at approximately $4.8 billion. The awards for drillships, jack-up platforms, and offshore facility services expand the company’s committed activity and support its operations for the coming years.
Source: Offshore Engineer