VAALCO Energy closed its Phase 3 drilling campaign in Gabon with the ETSEM-3H well in production and began a new stage of drilling in the Baobab field, off the coast of Ivory Coast.
The US company completed the offshore program in the SE Etame field after drilling, completing, and bringing the ETSEM-3H development well into production. Its initial stabilized rate reached approximately 2,000 gross barrels of oil per day.
Of that volume, approximately 1,140 barrels per day correspond net to VAALCO Energy.
The result marks the end of the Phase 3 campaign in Gabon. Following the completion of the work, the self-elevating platform Norway Borr Drilling was withdrawn from the field.
VAALCO Energy completes its drilling in Gabon
The ETSEM-3H well was located in a structurally elevated position within the SE Etame field. During drilling, the well encountered approximately 300 meters of net productive thickness along its lateral section in high-quality sands of the Gamba reservoir.
This configuration allowed for the incorporation of new production into the asset and the completion of the drilling program planned for this phase.
George Maxwell, CEO of VAALCO Energy, said the company is pleased with the results obtained at the well and confirmed that the unit is already producing around 2,000 gross barrels per day.
With the ETSEM-3H now operational, the company is now focusing part of its development activity in Ivory Coast.
Baobab begins a new phase of offshore drilling
Off the coast of Ivory Coast, VAALCO Energy began operations for Phase 5 of the Baobab field.
The campaign began with the sequential drilling of the upper sections of the new wells. Once these initial stages are completed, the company plans to finish each well and bring it into production gradually.
The program includes four production wells, three water injection wells, and two workovers.
Likewise, VAALCO expects to incorporate the first new producing well towards the end of 2026.
The company expects this campaign to generate production increases during 2027 as the new wells come online.
VAALCO Energy seeks to increase production and reserves
The activity in Gabon and Ivory Coast it is part of VAALCO Energy’s broader portfolio of production, development and exploration assets in Africa.
The company maintains operations in Gabon, Egypt, Ivory Coast, and Equatorial Guinea. Its strategy combines producing assets with new development projects supported by existing infrastructure.
The completion of Phase 3 in Gabon allows VAALCO to move on to the next stage of its organic program as Baobab gains prominence within its growth plans.
With Phase 5 now underway, attention is shifting to the pace of completion of the new wells and the contribution they can make to 2027 production.