Atmos Renewables, an Australian renewable energy company backed by Igneo Infrastructure Partners, has reached the Financial closing of the Teebar BESS project, of 400 MW and 1,600 MWh this development will take place in Queensland, Australia. This progress is part of a larger operation that also includes the 470 MW Parron Maam Marang wind farm, located in Western Australia.
Both facilities are backed by Capacity Investment Scheme (CIS), an Australian Government program that seeks to facilitate investments in renewable generation and electricity storage, contributing to strengthening the capacity of the country’s energy system.
Teebar BESS will store energy for four hours
The Teebar BESS project will be located next to the Teebar Creek substation, operated by Powerlink, in the Fraser Coast region of Queensland. Its development will add new storage capacity to an area connected to the existing electricity transmission infrastructure.
The facility will have a power output of 400 MW and an energy capacity of 1,600 MWh, which means it will be able to supply electricity for four consecutive hours when operating at its nominal power.
This capacity will allow electricity to be stored during periods of high availability and returned to the grid when consumption increases or renewable generation decreases.
In this way, Teebar BESS will help manage variations between supply and demand, providing greater flexibility to the operation of Australian electrical system it will also facilitate the use of energy from renewable sources, whose production depends on weather conditions.
The financial close includes a 470 MW wind farm
Together with Teebar BESS, Atmos Renewables confirmed the financial closing of Parron Maam Marang wind farm, which will have an installed capacity of 470 MW and will be located in the Wheatbelt region of Western Australia.
The energy generated by this park will be sold through a long-term electricity purchase agreement (PPA) with Synergy, one of the leading electricity trading companies in the state.
This agreement will allow the establishment of a commercial relationship for the sale of the planned electricity production, a relevant aspect to support the financial viability of renewable generation projects.
Although both facilities will be developed in different regions of Australia, they are part of Atmos strategy to expand its participation in the energy market through generation assets and storage.
The company will retain ownership of both projects during their construction and will be responsible for operating them once they begin providing service.
Atmos Renewables reaches 970 MW of projects backed by the CIS
With the financial closing of Teebar BESS and Parron Maam Marang, Atmos Renewables now has 970 MW of projects backed by the Capacity Investment Scheme that have completed this financial stage in the last 16 months.
The total also includes Merredin BESS, a 100 MW and 400 MWh storage facility whose financial closure was finalized in June 2025.
The three developments reflect the progress of the company’s portfolio, which combines different technologies to meet the needs of the Australian electricity system.
Nigel Baker, CEO of Atmos Renewables, emphasized the importance of overcoming the necessary processes to transform these initiatives into viable projects. Among the key aspects he mentioned were access to financing, formalizing commercial agreements, and obtaining grid connections.
These steps are especially relevant at a time when Australia needs to incorporate new energy infrastructure to meet the growth of the electricity demand and progressively compensate for the retirement of conventional power plants.
Energy storage is gaining prominence in Australia
Atmos Renewables currently has a national portfolio that exceeds 1.5 GW of wind, solar and energy storage projects, including facilities that are already operational and others that are under construction.
The company is backed by Igneo Infrastructure Partners, an investment manager specializing in infrastructure whose investors include entities such as MLC and CBUS.
Within this portfolio, Teebar BESS stands out for its ability to supply energy for four hours, a feature that will allow stored electricity to be moved from periods of lower demand to times when the system needs a greater supply.
The development of these types of facilities is becoming increasingly important as the share of renewable energy in Australia’s electricity mix grows. Batteries allow for better use of available generation capacity and offer a more flexible response to fluctuations in consumption.
With financing secured, Teebar BESS and Parron Maam Marang have passed a crucial milestone in their progress toward construction and future operation. Both projects are part of Atmos Renewables’ expansion and Australia’s efforts to add new clean energy generation and storage capacity to its electricity infrastructure.
Source: Renewables Now