- PowerChina combines 900 MW of photovoltaics and 100 MW of concentrated solar power
- How does molten salt thermal storage work?
- A 219-meter solar tower and more than 10,000 heliostats
- PowerChina's solar project on the Talatan plateau
- The plant will produce about 2.2 TWh of electricity per year
- China aims to expand its concentrated solar power (CSP) capacity to 15 GW by 2030
PowerChina China has commissioned its new 1 GW hybrid solar power plant in Gonghe County, Qinghai Province, northwest China. The facility combines photovoltaic generation with concentrated solar power (CSP) technology and a thermal storage system using molten salts. The complex reached full grid capacity on October 1, 2026. According to Chinese state media, this is the country’s first gigawatt-scale project integrating photovoltaics, concentrated solar power (CSP), and heat conversion.
PowerChina combines 900 MW of photovoltaics and 100 MW of concentrated solar power
The new plant has an installed capacity of 1,000 MW, distributed between a 900 MW photovoltaic park and a 100 MW solar thermal tower plant. The photovoltaic area comprises approximately 1.9 million solar modules, with a capacity of 900 MW in alternating current and approximately 1.25 GW in direct current.
Both technologies serve complementary functions; while the panels produce electricity directly from sunlight, the solar thermal unit can store energy in the form of heat and use it later to generate electricity, even when radiation decreases. This integration allows for better management of available energy throughout the day. Furthermore, the complex is part of the second group of large wind and solar power plants that China is developing in its northern and western regions.
How does molten salt thermal storage work?
One of the most outstanding elements of the installation is its eight-hour thermal storage system associated with the 100 MW concentrated solar power plant. The process is based on the use of molten salts, which are capable of storing large amounts of thermal energy. When electricity needs to be generated, the stored heat is used to produce steam, which then drives a turbine connected to an electric generator.
This system is complemented by a 20 MW electric heater, designed to utilize surplus production from the photovoltaic park. Instead of wasting this electricity, the equipment transforms it into heat and transfers it to the molten salts. This allows the storage system to receive energy from both concentrated solar radiation and surplus photovoltaic electricity, expanding the possibilities for utilizing the renewable resources.
This configuration can also help reduce generation cuts that occur when renewable electricity supply exceeds demand or grid evacuation capacity. It’s important to note that the eight hours of storage specifically correspond to the 100 MW concentrated solar power (CSP) unit and not to the entire 1 GW hybrid plant.
A 219-meter solar tower and more than 10,000 heliostats
The central element of the solar thermal infrastructure is a 219-meter-high receiving tower, surrounded by a field of 10,310 pentagonal heliostats collectively, the mirrors provide a reflective surface area of approximately 500,000 square meters. Each heliostat adjusts its orientation following the sun’s position to concentrate the radiation onto the receiver located at the top of the tower.
At that point, concentrated solar power is used to heat the molten salts, the heat can then be stored until it is needed to produce steam and operate the 100 MW turbine. Thanks to this mechanism, the facility can shift part of its electricity generation to peak afternoon demand hours or to periods with lower solar radiation; however, this flexibility depends on the amount of thermal energy available in the storage system.
PowerChina’s solar project on the Talatan plateau
The development of the facility involved several companies in the group PowerChina New Energy it was in charge of the development, investment and operation of the project, while Northwest Engineering Corp. assumed the functions of engineering, procurement and construction (EPC) contractor. The works were carried out on the Talatan Plateau, a high-altitude region where low winter temperatures and demanding weather conditions posed challenges for the construction work.
The design of the photovoltaic park also incorporates measures to promote coexistence between electricity generation and traditional livestock activities in the area. To this end, support structures of varying heights were used to preserve pastureland and maintain adequate spaces for livestock to continue grazing under the solar modules. In this way, the project seeks to harness the region’s energy potential without completely displacing the usual uses of the land.
The plant will produce about 2.2 TWh of electricity per year
PowerChina’s forecasts indicate that the complex will be able to generate around 2.2 TWh of electricity per year this production will contribute to the region’s renewable energy supply, according to the company’s calculations, this generation volume would prevent the annual consumption of approximately 690,000 tons of standard coal.
PowerChina also estimates that the facility could reduce carbon dioxide emissions by about 2.07 million tons per year, compared to the energy scenario used as a reference, these estimates highlight the project’s potential to replace some fossil fuel-based generation and increase the share of renewable sources within the electricity system.
In addition to production capacity, the combination of technologies allows for a more flexible use of solar energy, especially during periods when photovoltaic generation begins to decline.
China aims to expand its concentrated solar power (CSP) capacity to 15 GW by 2030
The commissioning of this power plant coincides with China’s efforts to expand the development of concentrated solar power and strengthen its integration into the electrical system. In December 2025, the National Development and Reform Commission (NDRC) and the National Energy Administration (NEA) published new guidelines aimed at boosting the growth of this technology.
Among the established goals is to achieve approximately 15 GW of installed solar thermal capacity by 2030 along with a progressive reduction in generation costs to approach those of coal-fired power plants, PowerChina’s project is also integrated into a larger concentrated solar power (CSP) development in Gonghe. Two other independent CSP plants, of 50 MW and 100 MW, are located in the same area, but their capacities are not included in the new 1 GW hybrid complex.
With its commissioning, the plant represents a step forward in the integration of photovoltaic generation, concentrated solar power, and thermal storage. Its configuration offers an alternative for harnessing surplus solar energy and extending the availability of renewable electricity beyond peak sunlight hours.