Germany will auction 4 GW of offshore wind energy in 2027

Germany is reorganizing five North Sea sites to auction 4 GW of offshore wind capacity in 2027 and improve its efficiency.
Offshore wind energy con aerogeneradores y plataformas eléctricas offshore sobre el mar.

Offshore wind energy in Germany is preparing a new round of auctions for 2027, offering 4 GW of capacity across five areas in the North Sea, this initiative is part of a review of maritime planning aimed at making better use of wind resources and improving conditions for the development of future wind farms.

The German Federal Maritime and Hydrographic Agency (BSH) published the second amendment to the 2025 Site Development Plan, called Flächenentwicklungsplan (FEP). The update introduces changes to the delimitation of certain areas and adjusts the award and commissioning schedules for several projects.

With these modifications, German authorities seek to ensure that the growth of installed capacity is accompanied by better energy efficiency. To this end, the new planning pays special attention to the distance between installations and to the production losses that can occur when wind turbines operate too close to each other.

Offshore wind energy in Germany will have five areas up for auction

The Federal Networking Agency Germany (BNetzA) will be responsible for organizing the tenders for the five sites planned for 2027, which have a combined capacity of 4,000 MW. The selected areas are N-10.1, N-10.2, N-10.3, N-13.1, and N-13.2, all located in German waters of the North Sea. These sites are part of the national strategy to increase electricity generation through offshore wind farms.

One of the most significant adjustments is concentrated in area N-10, whose surface area was expanded and subsequently divided into three sites. This distribution will allow for more space to arrange the wind turbines and reduce potential interference between future wind farms. The change also offers developers new conditions for designing their facilities. Having better-distributed areas can facilitate site selection and contribute to more accurate estimates of expected electricity production over the projects’ lifetime.

However, the 4 GW announced corresponds to capacity that will be offered in the auctions, not to facilities that will begin producing electricity in 2027. The awarded projects must subsequently complete their respective stages of development, construction and commissioning.

BSH modifies the design to better harness the wind

The plan revision incorporates an important technical criterion such as reducing energy losses associated with the wake effect, one of the factors that can affect the performance of the offshore wind farms this phenomenon occurs when a turbine extracts energy from the wind to generate electricity. As the airflow passes through the rotor, it loses speed and becomes more turbulent, which can damage other wind turbines located behind it.

If a second turbine receives that altered wind, its output can decrease, the magnitude of the losses depends on the prevailing wind direction, the spacing between turbines, and their arrangement within each wind farm. For this reason, the expansion of the N-10 area aims to provide greater flexibility in distributing wind turbines. With more space available, developers can study configurations that reduce interference and promote more efficient use of wind resources.

BSH President Helge Heegewaldt emphasized the need to consider the efficient use of installed capacity when planning offshore areas designated for power generation. This approach highlights a fundamental issue for the sector: increasing installed megawatts does not always translate into a proportional increase in electricity production. The location of the wind farms, their spacing, and wind conditions also directly influence their performance.

Sites N-12.4 and N-12.5 are postponed

The second amendment to the FEP also introduces adjustments to the timetable for other planned North Sea projects. Among the announced decisions, the postponement, until further notice, of the tendering and commissioning of sites N-12.4 and N-12.5 stands out.

According to BSH, this measure aims to promote the use of wind power by neighboring wind farms, the intention is to prevent an excessive concentration of wind turbines in close proximity from negatively impacting overall electricity production. Therefore, the planning considers not only the individual potential of each site, but also the possible interactions with surrounding facilities.

Another change affects the N-6.8 area, whose bidding and commissioning schedule is delayed by two years, until 2030. According to the information published on the review, this adjustment will allow for a more even distribution of offshore wind capacity growth over the next few years.

The changes reflect a reorganization of both the available spaces and the planned development dates, for interested companies, both factors are relevant, as they influence investment planning, bid preparation, and the scheduling of future projects.

The 2025 auction ended with no bids for 2.5 GW

The decision to modify the allocation schedule also comes after a call for bids that failed to attract proposals from developers. In August 2025, Germany auctioned 2.5 GW of offshore wind capacity at sites N-10.1 and N-10.2. However, the process ended without receiving any offers.

The lack of participants highlighted the difficulties the sector faced in committing new investments under the conditions established in that tender. Following this outcome, the German government decided to postpone the next call for tenders in these areas until 2027. This delay allowed time to move forward with reviewing the auction system and making adjustments to maritime planning.

Now, sites N-10.1 and N-10.2 will again be part of a tender, this time together with N-10.3, N-13.1 and N-13.2, within a modified territorial distribution. The response from companies in 2027 will allow an assessment of whether the changes introduced contribute to regaining the interest of developers.

Although better organization of areas can improve project efficiency, participation in auctions will also be influenced by other factors, including investment costs, revenue expectations, and the financial and regulatory risks associated with offshore park construction.

The industry is calling for contracts for difference and greater competition.

The German Offshore Wind Energy Association (BWO) welcomed the announced changes to the development plan. The organization particularly highlighted the expansion of the N-10 area, the division of large areas into smaller sites, and the incorporation of criteria aimed at improving energy efficiency.

Its CEO, Stefan Thimm, noted that projects of approximately 1 GW can offer better opportunities to foster competition and facilitate the participation of different companies in upcoming tenders. As part of its proposals, the association suggested limiting awards to one site per participant in each round. This measure aims to prevent a single company from securing multiple projects and broaden access for other developers.

The BWO also requested the incorporation of an auction system based on contracts for difference (CfDs), accompanied by indexation mechanisms that allow for the consideration of changes in certain costs. These contracts establish a reference price for the electricity generated. Depending on the terms of the mechanism, the developer can receive compensation when the market price falls below the agreed-upon value and make refunds when it exceeds it.

The aim is to reduce some of the uncertainty associated with fluctuations in the electricity market, a relevant factor for facilities requiring significant investment and long development periods. From the association’s perspective, a scheme of this kind could offer greater financial predictability and help restore investor interest.

For now, these proposals are part of the debate on reforming the offshore wind energy allocation system in Germany. Their eventual implementation will depend on the decisions made by the regulatory authorities.

Germany maintains its goal of reaching 70 GW by 2045

The adjustments to the upcoming auctions come at a time when Germany is looking to further expand its offshore wind power generation capacity. According to data released by BSH, the country currently has 11.49 GW of installed capacity at sea.

National targets aim to reach 40 GW by 2035 and increase that figure to 70 GW by 2045, achieving these goals will require developing a significant amount of new infrastructure over the coming decades. To accomplish this, simply identifying and allocating new offshore areas will not be enough. Projects must also be viable for companies and be able to progress from planning to construction and commissioning.

The North Sea and the Baltic Sea will remain key areas for this expansion, however, the exploitation of their resources will depend on an appropriate distribution of the parks and on conditions that allow for the mobilization of the necessary investments.

In this context, the FEP modification introduces a perspective that goes beyond simply increasing authorized capacity, the planning seeks to pay closer attention to the electricity production that the parks can achieve and how their locations influence overall performance.

The 2027 tender will be an opportunity to see how the market responds to this reorganization, developer interest and the results of the awards will allow us to assess the scope of the changes introduced and their contribution to Germany’s offshore wind expansion goals.

Source: Offshore Wind

Photo: Shutterstock

Verified Author

Moises Carrasquero is a mechanical engineer and writer specializing in technology, engineering, and industrial development, with a focus on the advancements that are transforming these sectors. My goal is to turn complex technical information into clear, accurate, and relevant journalistic content.