The Australian company Mint Renewables received urban planning approval to develop Kojonup BESS a 100 MW, 800 MWh battery energy storage system in Western Australia has been authorized. The authorization, granted by the Regional Development Assessment Panel (DAP), represents a step forward for a facility designed to supply electricity for eight hours at its nominal capacity.
The project will be located near Kojonup, in the Great Southern region, approximately 241 kilometers southeast of Perth. Although it already has planning permission, its construction still depends on other authorizations and the finalization of its connection to the electricity grid.
Kojonup BESS will have a storage capacity of 800 MWh
According to the documentation submitted to local authorities in May, the facility will be built about three kilometers northwest of Kojonup, on land primarily intended for agricultural activities.
The site covers approximately 34.5 hectares, although the area directly affected by the construction will be around 8.1 hectares. Much of the land has already been cleared, allowing for the reuse of a previously developed area.
One of the main features of the project is its ability to store 800 MWh of energy and deliver a power of 100 MW for eight continuous hours, according to its design.
This autonomy places Kojonup BESS within the long-duration energy storage segment, a technology that allows electricity to be shifted between different times of the day and contributes to the stability of the electrical system.
The electrical connection will be made through a 132 kV substation
The proximity to the existing Kojonup substation was one of the factors considered in selecting the site, the design includes building a new substation within the project, where the voltage will be increased from 33 kV to 132 kV. From there, the power will be transported via underground cables to the existing connection infrastructure.
However, Mint Renewables continues discussions with Western Power, the electricity grid operator in southwest Western Australia, to establish the final connection terms.
For now, the proposed route remains provisional and could undergo modifications during the following stages of development.
Once connected, Kojonup BESS would be part of the South West Interconnected System (SWIS), which operates independently of the National Electricity Market in eastern Australia.
Mint Renewables expects to begin construction by the end of 2027
According to the schedule presented, construction work could begin during the fourth quarter of 2027, provided the project obtains the pending permits and meets the necessary conditions.
The works would last approximately 55 weeks, while the entry into service is planned for 2029, however, these dates could be adjusted as development progresses.
During construction, up to 110 jobs are planned, with an average workforce of 37 employees and periods of higher activity that could bring together 87 people simultaneously.
Furthermore, the company initiated a community participation process in September 2025, held three informational meetings in October, and conducted a survey to learn about residents’ concerns.
Among the issues raised were the prevention of forest fires, the use of water resources, the increase in traffic, and the potential economic benefits for the community.
Because the site is located in a fire-prone area, the project incorporates a risk management plan, it also contemplates the possible removal of approximately 0.09 hectares of native vegetation, subject to the necessary permits.
The 8 hours of storage respond to market demands
The planned duration of Kojonup BESS is especially important for its potential participation in the Western Australian Wholesale Electricity Market (WEM), operated by the Australian Energy Market Operator (AEMO).
In this market, the storage systems they must have a duration of at least six hours to be eligible for payments from the Reserve Capacity Mechanism, which is intended to remunerate the availability of electrical resources during periods of higher demand.
With an autonomy of eight hours, Kojonup exceeds that duration requirement, however, meeting this technical condition does not guarantee the allocation of capacity credits or the obtaining of commercial income.
An example of the importance of these requirements is the Waroona project, developed by Frontier Energy south of Perth. The company modified its initial configuration of 80 MW and 4.75 hours of storage to achieve a design of 81.5 MW and 562 MWh, equivalent to approximately 6.9 hours of autonomy.
To date, Mint Renewables has not reported on securing capacity credits for Kojonup, revenue commercial agreements, or financing mechanisms. It has also not disclosed the project’s estimated budget.
Mint Renewables is developing other battery projects in Australia
Kojonup BESS is part of a broader portfolio of solar, wind and energy storage initiatives that Mint Renewables is developing in different regions of Australia.
In Victoria, the company is working on Dederang BESS, a 200 MW and 400 MWh facility whose authorization process was accelerated by the state government in 2025 through the Development Facilitation Program.
Although the proposal faced opposition from the local council, it continued its processing under that mechanism. Planning documents estimate an investment of approximately 280 million Australian dollars.
Meanwhile, in New South Wales, Mint Renewables is developing Magpie Hill, a hybrid project that includes up to 375 MW of solar generation and a 375 MW, 3,000 MWh storage system. Construction is scheduled to begin in mid-2028.
With the urban planning approval for Kojonup BESS, the company takes another step in expanding its grid-scale energy storage portfolio. The next phase will depend on obtaining the remaining permits, connection agreements with Western Power, and securing the necessary commercial terms to finalize the investment.
Source: Energy Storage