Marinus Link begins work in Tasmania to connect 1.5 GW to Victoria

The Marinus Link interconnector begins a new phase of construction to connect 1.5 GW of electrical capacity between Tasmania and Victoria.
Vista aérea de una subestación eléctrica de alta tensión, infraestructura similar a la prevista para el proyecto Marinus Link en Australia.

He Marinus Link project progress is being made in Australia with the start of a new phase of construction in northwest Tasmania. The infrastructure will expand electricity exchange with Victoria via a high-voltage submarine cable, with a total planned capacity of 1,500 MW.

The breakthrough was unveiled at a ceremony that brought together Federal Minister for Climate Change and Energy Chris Bowen, Tasmanian Premier Jeremy Rockliff, and Marinus Link Chair Sandra Gamble. Roger Gill, Chairman of TasNetworks, was also in attendance.

With these projects, Australia seeks to strengthen its electricity transmission infrastructure and facilitate the use of Tasmania’s renewable resources to meet the energy demand of the mainland.

Marinus Link will have two phases of 750 MW

The new interconnector will use technology from high-voltage direct current (HVDC) to transport electricity between northwest Tasmania and the Latrobe Valley in Victoria.

Its development includes two phases of 750 MW each, until reaching a total capacity of 1,500 MW, according to the project schedule, the first stage should become operational by the end of 2030.

One of the main advantages of this infrastructure will be its ability to transmit electricity in both directions, this will allow Tasmania to export energy to Victoria when it is available and to receive electricity from the mainland when needed. This flexibility will help balance supply and demand within Australia’s National Electricity Market (NEM).

Currently, Tasmania is already connected to the mainland via Basslink, a 500 MW interconnector, with Marinus Link, the possibilities for electricity exchange between the two states will be considerably expanded.

Battery of the Nation will expand hydroelectric storage

The development of Marinus Link is related to Battery of the Nation, an initiative by Hydro Tasmania that seeks to harness the state’s hydroelectric potential and expand its energy storage capacity.

The plan presented in 2022 contemplates incorporating between 1.5 and 3.5 GWh of storage through pumped hydroelectric projects.

This technology works by using electricity to pump water to a reservoir located at a higher elevation. when energy demand increases, the stored water is released through turbines to generate electricity.

In this way, pumped hydroelectric systems can store surplus energy and provide generation when other renewable sources, such as solar and wind power, reduce their production.

In this scenario, Marinus Link will play an important role in facilitating the exchange of electricity between Tasmania and Victoria while storage facilities will allow for better use of available energy resources.

TasNetworks is carrying out new electricity transmission works

Alongside the development of the interconnector, TasNetworks is progressing with the Northwest Transmission Works (NWTD), which are designed to strengthen Tasmania’s electricity grid and adapt it to the needs of the project.

The first stage comprises approximately 130 kilometers of transmission infrastructure and is scheduled to enter service during 2030.

Work has already begun between Sheffield and Burnie, with activities including enabling access, installing fences, building foundations for electrical towers and modifications to the Sheffield substation.

During 2027, work will also be intensified on the cables and converter stations in Heybridge, Tasmania, and Hazelwood North, Victoria.

In Victoria territory, the project includes a landing point on the coast at Sandy Point, facilities in Mardan and approximately 90 kilometers of underground cable in Gippsland.

These works will allow the HVDC infrastructure to be connected to the existing electrical networks and prepare the system for the exchange of energy between both states.

Marinus Link surpasses 5 billion Australian dollars in construction

The first phase of the project, together with the associated transmission works, represents one of the most significant investments aimed at expanding the electrical infrastructure between Tasmania and Victoria.

According to the updated cost-benefit analysis cited by the project, the combined construction costs of the first stage of Marinus Link and the NWTD works exceed 5 billion Australian dollars.

To support its implementation, the Clean Energy Finance Corporation (CEFC) committed 3.8 billion Australian dollars through the Rewiring the Nation program, an initiative aimed at financing improvements in the electrical infrastructure.

Furthermore, a joint venture between Gamuda and Samsung C&T received a contract worth 994 million Australian dollars to carry out civil, structural and electrical work, including the construction of buildings for converter stations.

The project’s progress is also starting to generate activity among regional suppliers, according to Marinus Link, so far 119 companies and suppliers have been contracted, 59 of which are from North and Northwest Tasmania.

The interconnector could reduce wholesale electricity prices

In addition to expanding transmission capacity, Marinus Link could help reduce wholesale electricity prices in connected states. The developer’s estimates project a decrease of approximately 15 Australian dollars per MWh in Tasmania and 17 Australian dollars per MWh in Victoria.

However, these figures represent projections subject to future electricity market conditions and the behavior of the system once the infrastructure is operational.

Regarding the authorizations, the project obtained a federal transmission and infrastructure license in September 2026, in accordance with the Australian regime applicable to marine electrical installations.

This permit adds to the federal environmental approval and the final investment decision adopted in August 2025, two events that allowed progress to the construction stage.

With new works underway and the first phase planned for completion by the end of 2030, Marinus Link continues its development as a strategic infrastructure to expand electricity transmission between Tasmania and Victoria, facilitate the integration of renewable energy and support Battery of the Nation’s future hydroelectric storage projects.