Energean progresses with the development of Katlan through the simultaneous execution of deep-water drilling work, installation of underwater infrastructure and modernization of its floating production, storage and offloading (FPSO) unit in the Eastern Mediterranean.
The gas project, valued at $1.2 billion with full financing, it aims to achieve first gas production during the first half of 2027. If the planned schedule is met, production would begin less than two years after the final investment decision.
Katlan will allow the incorporation of around 26 billion cubic meters of gas, strengthening Energean image in a region where several operators are increasing their investments in exploration and production.
Energean runs three lines of work in parallel
Unlike the sequential scheduling commonly used in many offshore projects, Energean it develops in parallel three fundamental components of Katlan, one is the drilling of wells in deep waters, the installation of underwater infrastructure and the necessary modifications to the FPSO.
These activities are often interdependent: drilling provides information about reservoir behavior, while subsea systems transport production to surface facilities. The FPSO then receives and processes the hydrocarbons.
Performing these operations simultaneously can reduce the time required to bring the field to the production stage. However, this strategy also demands closer coordination, as any technical or engineering modifications could impact several areas of the project at once.
Katlan control speeds up decision-making
Energean maintains a 100% operating participation in Katlan, a structure that facilitates coordination and decision-making during project execution.
By not relying on partners within a joint venture, the company can directly manage approvals, engineering resources, and potential scope changes.
This control becomes especially important when different contractors and teams are working simultaneously on wells, subsea systems, and processing facilities.
The strategy also reflects Energean interest in maintaining its own operational capacity in deepwater projects in this way, the company concentrates both the economic potential of the development and the risks associated with its execution.
The FPSO increases its processing capacity
While work on Katlan progresses, the modernization of the FPSO has already allowed for an expansion of its total liquid processing capacity, which went from 18,000 to 31,000 barrels per day, an approximate increase of 72%.
This additional capacity also benefits production from Karish y Karish North, two assets connected to Energean’s infrastructure in the area.
At the same time, increased liquid production raises the company’s exposure to price fluctuations international oil prices the Brent futures contract for the following month was around $100.81 per barrel on October 6, 2026, according to the data included in the reference material.
Katlan raises Energean investment in the Eastern Mediterranean
With the development of Katlan, Energean committed investment in the Eastern Mediterranean exceeds $4 billion. The company thus maintains its strategy of retaining operational control of its assets, directly assuming a larger proportion of the risk instead of distributing it through the sale of shares.
The project is also progressing at a time of increasing gas activity in the Eastern Mediterranean, where different companies are developing new projects while countries in the region seek to expand their participation in the energy market.
New gas projects are progressing in the Eastern Mediterranean
These developments include Cronos located in Block 6 off the coast of Cyprus, Eni and TotalEnergies made the final investment decision on the project on July 28, 2026, with the aim of starting gas production in 2028.
According to available information, Cronos contains more than 3 trillion cubic feet of gas and could reach a production close to 500 million cubic feet per day.
In September, McDermott received a contract from Eni related to management, engineering, equipment and materials procurement and installation for development.
Besides, Chevron as it made progress in its expansion into Greek waters during 2026, the company requested to acquire a 70% operating stake in an exploration block southwest of Greece, while Helleniq Energy would retain the remaining 30%.
Regional gas gains importance in the energy strategy
The increase in offshore activity coincides with European efforts to diversify their energy supply sources, within this context, Greece is expanding its importance as a transit point for gas destined for other markets on the continent.
The Greece-Bulgaria Interconnector (IGB) operated with an approximate capacity of 3 billion cubic meters per year meanwhile, work is progressing to increase it to 5 billion cubic meters per year through improvements in compression and measurement infrastructure.
Katlan is primarily focused on supplying gas through contracts in Israel and other regional markets, so variations in major European hubs do not directly determine the project’s economic viability.
Even so, the growth in production in the Eastern Mediterranean expands supply alternatives and reinforces the importance of a region that is increasingly concentrating investments in gas exploration, production and infrastructure.
Source: EnergyReader.io