He electrical interconnector the project between Spain and France is already 70 % complete, with work progressing on the laying of high-voltage land and submarine cables. Valued at 3.1 billion euros, the project will increase the electrical exchange capacity between the two countries from 2.8 GW to 5 GW, the Spanish electricity grid has begun installing underground high-voltage direct current (HVDC) cables in Spanish territory.
This phase will allow the future Gatika converter station to be connected to the coast of Lemoiz, in Biscay, where the land infrastructure will link with the submarine cables, the route will cross the Bay of Biscay to connect Gatika, in Spain, with Cubnezais, in France. Once operational, the link will strengthen the electricity transport capacity between both countries and facilitate the exchange of energy between their networks.
Spain-France Interconnector Submarine Cable Laying Progresses
In parallel with the land-based work, Red Eléctrica has completed the second phase of submarine cable installation. This operation comprised a 50-kilometer stretch, laid by the cable-laying vessel Monna Lisa, belonging to Prysmian. The first phase was completed in August, when the vessel Victoria, from the company NKT, laid the first 65 kilometers of the route off the coast of Biscay.
With these two operations, the installation of the submarine cables for this section of the Bay of Biscay has been completed. However, work remains to be done in other areas along the route. Operations off the coast of Gipuzkoa will continue between November and February, while the installation of the sections in French waters is scheduled to continue until the summer.
Construction of the Gatika converter station is progressing
Furthermore, Red Eléctrica has announced new progress in the construction of the Gatika converter station. The civil engineering works have been completed, and current work is focused on the electromechanical assembly of the facilities. This station will be a key component for connecting the electrical systems of both countries using HVDC technology.
From there, the underground cables will travel approximately 13 kilometers to reach the coast of Lemoiz. The progress of this installation, along with the laying of the land and submarine cables, will allow the various components of the interconnection to be completed progressively.
Red Eléctrica and RTE are developing the project with European support
The Bay of Biscay interconnector is being jointly developed by Red Eléctrica and its French counterpart, RTE, through the joint venture Inelfe European Union this infrastructure has been recognized as a Project of Common Interest (PIC). Furthermore, it is financed by CINEA, the European Climate, Infrastructure and Environment Executive Agency, and backed by the European Investment Bank (EIB). When operational, the connection will increase the electricity exchange capacity between Spain and France from 2.8 GW to 5 GW. This increase will strengthen the connection between the two national grids and expand the possibilities for electricity transmission within the European energy system.
Source: Offshore Energy
Photo: Red Eléctrica