Hanhikivi-1: Rosatom Announces Favorable Ruling Over €7 Billion Nuclear Power Plant

Rosatom announces a favorable arbitration ruling in the dispute over Hanhikivi-1, a canceled 1,200 MW nuclear power project in Finland. The case highlights contractual risks, EPC obligations, and challenges facing major energy infrastructure investments.
Hanhikivi-1 nuclear power plant project site in Finland with preliminary construction works and auxiliary facilities

Rosatom announced a favorable arbitration ruling in the dispute over Hanhikivi-1, the planned 1,200 MW nuclear power plant in northern Finland, valued at approximately €7 billion. According to the Russian corporation, a tribunal of the International Chamber of Commerce (ICC) determined that Fennovoima had improperly terminated the contract in 2022, a decision that could influence the outstanding financial claims between the two parties.

The ruling, announced on October 10, 2026, marks a new chapter in a dispute involving engineering, procurement, and construction (EPC) contracts, supply obligations, and risks associated with major energy investments. However, the full text of the arbitration award has not been publicly disclosed, and Fennovoima had not issued a response at the time of the Reuters report.

Hanhikivi-1 and the Origins of the Contractual Dispute

The project involved installing a 1,200 MW nuclear unit in Pyhäjoki, Finland, under a contract signed in 2013 with Rosatom’s participation. Its development required completing engineering, licensing, and infrastructure preparation processes before construction of the power plant could begin.

In May 2022, Fennovoima terminated the EPC contract with RAOS Project, a company affiliated with Rosatom. At the time, the Finnish company justified its decision by citing accumulated delays, difficulties in executing the project, and increased risks arising from the war in Ukraine.

The cancellation interrupted design and licensing activities associated with the Russian supplier. Fennovoima subsequently withdrew its construction license application from the Finnish authorities, meaning the plant never reached the reactor construction stage.

The case contrasts with other nuclear programs that have progressed to physical construction, such as Rosatom’s construction of new nuclear units at the Leningrad Nuclear Power Plant, where meeting construction milestones forms part of industrial planning.

Arbitration Reopens the Debate Over EPC Contracts

According to Rosatom, the arbitration tribunal concluded that Fennovoima had improperly terminated the contract and that the project was making satisfactory progress when the cancellation occurred. These conclusions reflect the account provided by the Russian company and have not been independently verified against the full text of the ruling.

The dispute also involves substantial financial claims. In 2025, Rosatom filed a lawsuit in Moscow seeking approximately $2.8 billion from Finnish companies associated with the project. Fennovoima, meanwhile, had initiated proceedings to recover advance payments and claim damages resulting from breaches it attributes to the supplier.

These amounts represent claims made by the parties, not compensation definitively awarded through the October 10 announcement.

In energy projects, EPC contracts establish responsibilities for engineering, procurement, construction, schedules, and delivery conditions. Their importance is also evident in initiatives across other industries, such as the award of the EPC contract for the North Field West liquefied natural gas expansion in Qatar, where coordination across multiple disciplines determines the execution of large-scale infrastructure.

What Does the Ruling Mean for the Nuclear Industry?

The main consequence of the announcement is not the potential revival of Hanhikivi-1, but rather the debate over how responsibilities are allocated when a nuclear project is canceled before construction begins.

For facilities of this nature, assessing contractual compliance may involve engineering documentation, technical deliverables, approved schedules, licensing progress, supply commitments, and communications between the project owner and contractor.

The existence of delays does not, by itself, determine the responsibility of either party. The agreed contractual obligations, causes of the delays, and specific conditions permitting contract termination must also be examined.

The regulatory component is particularly important because nuclear construction depends on authorizations that are independent of commercial commitments. This relationship between permitting and project execution can be observed in TerraPower’s Natrium project, which received authorization to build its reactor in Wyoming.

In the case of Hanhikivi-1, the withdrawal of the construction license application confirms that the project ceased progressing through Finland’s regulatory process, regardless of subsequent developments in the arbitration disputes.

Litigation Continues After the Project Cancellation

Although Rosatom described the ruling as favorable, its Director General, Alexey Likhachev, acknowledged that legal proceedings related to the project are still ongoing.

The available information does not establish a definitive compensation award or support the conclusion that all claims have been resolved. There has also been no announcement regarding the restart of the power plant project.

For the nuclear industry, the Hanhikivi-1 case demonstrates the importance of maintaining verifiable records of technical progress, defining contractual termination mechanisms, and assessing regulatory and supply risks from the earliest stages of investment.

Resolving these disputes can take years, even after the engineering and construction activities planned for a facility have been canceled.