The two offshore substations for the Gennaker wind farm, located in Germany, have departed the Netherlands bound for the Baltic Sea. They are the OSS Zingst and OSS Darß facilities, which will enable the electricity generated by the wind project to be transmitted to Germany’s onshore grid.
The topsides and their respective steel jacket foundations were transported from the shipyards in Schiedam and Vlissingen. Both facilities are part of the OST-6-1 grid connection project, developed by transmission system operator 50Hertz.
With this operation, the project moves into a new phase of offshore work, after completing the manufacturing, assembly, and integration of its main electrical systems.
Gennaker’s substations will have 450 MW of capacity each
The OSS Zingst and OSS Darß platforms each have an approximate capacity of 450 MW and will collect and route the electricity produced by the offshore wind farm’s turbines.
The OSS Zingst substation left the Schiedam shipyard, while OSS Darß began its transport from Vlissingen on October 9. Previously, technical teams completed manufacturing and preparations for maritime transport.
In addition, each facility has an upper structure, known as the topside, which houses the main electrical equipment. It is supported by a steel jacket foundation, designed to provide stability to the platform once installed on the seabed.
These structures will be key to integrating offshore-generated electricity into Germany’s transmission system.
Smulders HSM and Iv execute the offshore substation contract
The construction and delivery of both facilities is being carried out by HSI Joint Venture, a joint venture formed by Smulders HSM and Iv.
The contract covers engineering, procurement, construction, transport, installation, and commissioning under the EPCIC model.
In September, the companies completed fabrication and the loading operations at the Dutch shipyards. Now, their teams will need to coordinate offshore installation maneuvers and the subsequent commissioning of the electrical systems.
Hans Leerdam, Commercial Director at Smulders HSM, noted that the transport of the substations reflects the joint work carried out across the project’s different phases.
The operation requires coordination among engineering, fabrication, and electrical integration teams due to the size of the structures and the conditions of their offshore installation.
The OST-6-1 project will connect Gennaker to the German grid
The OST-6-1 system, developed by 50Hertz, will connect the Gennaker offshore wind farm to Germany’s onshore power infrastructure.
Owned by Skyborn Renewables, the wind farm is located about 15 kilometers north of the Fischland-Darß-Zingst peninsula, off the coast of the German state of Mecklenburg-Western Pomerania.
The connection infrastructure is needed to transmit electricity from the offshore generation facilities to the transmission grid, where it can be distributed to consumption points.
In this way, the two substations are a central part of the electrical system that will enable the energy produced by the future wind farm to be utilized.
Gennaker targets 2027 for wind turbine installation
The Gennaker project includes the installation of 63 Siemens Gamesa wind turbines, whose construction and assembly involve various companies specializing in marine infrastructure.
Contractors include EEW Special Pipe Construction and Dajin Heavy Industry, responsible for manufacturing the monopiles and transition pieces. Seaway7, for its part, will take part in installing these structures.
Likewise, TKF and Boskalis will be responsible for supplying and installing the inter-array cabling, while Fred. Olsen Windcarrier will carry out the turbine installation operations.
According to the project schedule released, turbine installation will begin in 2027 and the wind farm is expected to enter operation in 2028.
As these preparations move forward, the transport of the OSS Zingst and OSS Darß substations allows work to continue on completing Gennaker’s grid connection. The next phase will focus on installing the structures in the Baltic Sea and integrating their systems ahead of the wind farm’s start-up.
Source: Marine Technology