Singaporean company Seatrium secured a contract worth more than 200 million Singapore dollars, about 156.52 million US dollars, to work on an FPSO unit for SBM Offshore that will be used for oil projects in South America.
The agreement includes modifications to the vessel, fabrication of structures, and installation of processing modules. Seatrium will also participate in pre-commissioning tasks and the necessary testing to prepare the facility for future operations.
The new order continues the relationship between the two companies, which have worked together on the construction and integration of floating facilities for the oil industry.
SBM Offshore commissioned Seatrium to carry out the engineering and integration work necessary to adapt the vessel to the operating conditions foreseen in the project.
A floating production, storage and offloading ( FPSO ) unit receives hydrocarbons extracted from underwater fields, processes the fluids, and stores the oil until it is transferred to transport vessels.
This type of facility is mainly used in marine fields where environmental conditions or distance from the coast make it difficult to transport production directly to land-based facilities.
SBM Offshore, a Dutch company specializing in floating production facilities , once again turned to Seatrium to carry out the integration activities.
For now, the announcement does not identify the oil field or the name of the FPSO unit that will receive these modifications.
Seatrium will be in charge of various interventions on the ship, from the manufacture of structural components to the assembly of the equipment that will allow the production operations to be carried out.
One of the planned activities is the construction of structures for the anchoring system, responsible for keeping the installation in position during offshore operations .
Supports will also be manufactured for the risers , which transport fluids from the underwater systems to the floating unit.
The contract includes the construction of the flare tower, used to manage the controlled combustion of gases during certain operating conditions, as well as the structures that will support the upper processing modules, known as topsides .
Furthermore, the Seatrium teams will carry out modifications to the vessel and dry dock work before completing the assembly of the modules.
Integrating FPSOs requires coordinating the vessel's systems with the production equipment. This includes hydrocarbon processing facilities and auxiliary systems involved in operations.
The work is scheduled to begin during the fourth quarter of 2026 and conclude in 2029, according to the schedule released by Seatrium.
During that period, the structural modifications and the integration of the equipment foreseen in the contract will be carried out.
Once these activities are completed, the company will carry out mechanical finishing work and certain pre-commissioning tasks. It will also provide support during operational testing and sea trials.
These checks will allow us to review the behavior of the installed systems and verify that the equipment is ready for the next stages of the project.
Although Seatrium plans to complete its work in 2029, a date for the start of commercial production of the unit has not yet been announced.
The relationship between SBM Offshore and Seatrium has a history in several offshore oil production projects, especially in Guyana.
One of them is the Jaguar FPSO, intended for ExxonMobil's Whiptail project . In 2024, Seatrium received a contract to manufacture and integrate upper modules for this facility.
Both companies have also collaborated on units such as Liza Destiny, Liza Unity, Prosperity and One Guyana, used in oil developments off the Guyanese coast.
Marlin Khiew, executive vice president of Seatrium Energy (Projects) and president for Latin America, noted that the award will allow them to take advantage of the experience gained in previous projects, especially in the execution of complex integration work.
The executive also highlighted the role that South America plays in the global energy supply and the importance of continuing to develop facilities that support deep-water operations.
With this new contract, Seatrium will add another project to its shipbuilding and integration portfolio. The work will last approximately three years and will focus on preparing a floating facility for future oil developments in the region.

The electrical interconnection project between Spain and France, across the Bay of Biscay, is now 70% complete. The infrastructure, requiring an investment of €3.1 billion, will increase the electricity exchange capacity between the two countries from 2.8 to 5 gigawatts (GW). As part of the work, Red Eléctrica has begun installing 13 kilometers of underground cables that will connect the Gatika substation to the coast of Lemoiz, Spain.
In the maritime section off the coast of Biscay, 115 kilometers of cables have already been installed. Work will continue off the coast of Gipuzkoa between November and February, while the work in French waters will extend into the summer. Meanwhile, the Gatika electrical substation has completed its civil construction phase and is now in the equipment installation stage. The project is being developed by Red Eléctrica and the French company RTE, with financial support from the European Union.
Renewable energy company Neoen secured AU$1.8 billion in loans from 13 financial institutions to support five clean energy projects in Australia. These include two wind farms, a solar power plant, and two battery storage systems, with a combined capacity of approximately 1.2 gigawatts (GW). The facilities include the Culcairn solar plant, the Goyder South wind farm, and the Hornsdale Power Reserve.
With this agreement, Neoen has now secured over AU$5 billion in financing since 2024. These funds support a total of 20 renewable energy and storage facilities, with a combined capacity of 4.7 GW. The company, which has developed more than 6 GW of energy capacity in Australia, plans to reach 10 GW by 2030. This latest transaction is the largest financing of its kind that it has secured in the country and will allow it to continue with its expansion plans.
Renewable energy company Econergy has acquired four battery energy storage facilities in England, with a total capacity of 106 megawatts (MW). The projects are already operational, and the company plans to expand their storage capacity from one to three hours. The transaction involves repaying a €25 million loan and an additional payment of up to €5 million, contingent upon obtaining the necessary permits and meeting the conditions required to carry out the expansions.
With this acquisition, Econergy expands its presence in the UK, where it already operates the 50 MW West Melton and 40 MW Dalmarnock facilities. It is also developing four other battery projects totaling 239 MW. The company expects the acquired assets to generate approximately £4.7 million in operating profit before interest, taxes, depreciation, and amortization (EBITDA) by 2027. However, the insolvency of the contractor responsible for building the facilities could complicate the management of certain guarantees and access to new financing.
North Sea oil and gas companies are experiencing a period of increased merger and acquisition activity, fueled by high energy prices and the need to cut costs. According to LSEG data cited by Reuters, these deals are projected to reach $19.6 billion by 2026, up from $16.5 billion in 2025. The rise in oil and gas prices, linked to the conflict between the United States, Israel, and Iran, has boosted company revenues and provided them with more resources to acquire other businesses.
Adding to this scenario is the high tax burden on the sector in the United Kingdom, where hydrocarbon exploration and production activities are subject to a nominal tax rate of 78%. This situation leads many companies to consider mergers as a way to share costs, take advantage of tax benefits, and maintain the profitability of their operations. Analysts consulted by Reuters indicate that smaller companies face greater difficulties in sustaining their operations, while larger operators have better conditions for acquiring and managing mature fields.