Offshore drilling has begun for the Coral North FLNG project in the Rovuma Basin, off the coast of Mozambique. Eni and its Area 4 partners are preparing up to six development wells that will supply natural gas to a new floating liquefaction facility.
drilling vessel SAIPEM 12000 , operated by ENH-Saipem Drilling Company, will be used to carry out the campaign . Work began on November 1, 2026, and is expected to last approximately ten months, according to forecasts released by Eni.
The activity is concentrated in the northern sector of the Coral field, where the reserves intended to supply the future LNG plant are located.
The program is organized in two phases. During the first phase, four production wells will be drilled, while the remaining two correspond to a second stage of development.
In addition to drilling into the seabed, the teams will need to complete the wells to prepare them for gas extraction. This work includes installing the necessary components to maintain operating conditions and control the flow of hydrocarbons to the production system.
According to Mozambique's National Petroleum Institute (INP) , the campaign is estimated to last 270 days. Eni, for its part, has indicated an approximate period of ten months for drilling and completion activities.
The six wells are part of the Coral North FLNG development, a facility designed to process natural gas directly offshore. It is scheduled to become operational in 2028.
The drilling vessel SAIPEM 12000 arrived in Cabo Delgado province on October 25, 2026. Two days later, official inspections began to verify that the vessel met the required conditions to work in Mozambican waters.
The INP teams reviewed aspects related to the ship's operation, worker safety, and environmental protection measures. National agencies responsible for health, labor, and emergency response also participated in the inspections.
The review of support facilities had begun days earlier. Between October 13 and 15, authorities inspected the logistics bases in Pemba, from where services will be provided to the drilling campaign.
These facilities are necessary to organize the supply of materials and meet the needs of the teams working offshore.
The program is being executed by ENH-Saipem Drilling Company , a joint venture that includes Mozambican participation in the operations. With this contract, a locally owned entity is assuming direct operational responsibilities for offshore drilling activities in the country for the first time.
While the SAIPEM 12000 works on the development of the wells, the construction of the floating unit that will receive the gas from the field continues.
At the end of October, the INP reported that the installation had reached an overall progress of 72% in the work carried out in South Korea.
The Mozambican government approved the project in April 2025. The unit will have a planned capacity of 3.55 million tons of liquefied natural gas per year.
Once installed in the production area, the infrastructure will receive the gas extracted from the wells, treat it, and cool it until it becomes liquid. Subsequently, the LNG can be transferred to specialized vessels for transport to its destination markets.
This floating production system allows processing and liquefaction to be carried out offshore, without the need to transport all the gas to an onshore plant beforehand.
The unit's construction schedule and drilling program are part of the planned development for Coral North to begin production in 2028.
Coral North will leverage the experience of the Coral South FLNG project, which began production in 2022 and became the first natural gas development in operation within the Rovuma Basin.
Since then, Coral South has shipped more than 175 cargoes of liquefied natural gas to the international market, according to data released by Eni.
With the addition of Coral North, the company expects the combined LNG production capacity in Mozambique to reach approximately 7 million tons per year.
This development involves Eni, China National Petroleum Corporation (CNPC), National Hydrocarbons Company (ENH), KOGAS and XRG.
The drilling campaign will continue over the next few months, while construction of the floating storage and offloading (FSOS) facility progresses. Production is scheduled to begin in 2028, when the new wells will be able to supply gas to Coral North FLNG.

Offshore drilling company Valaris secured new contracts and extensions worth approximately $600 million through August 2026. These agreements bring its order backlog to $4.8 billion, up from $4.6 billion previously. The new commitments include oil drilling operations in Suriname, Egypt, the Gulf of Mexico, and the Middle East.
Among the contracts secured is a three-year agreement with BP, valued at approximately $290 million, to provide services on the Mad Dog and Thunder Horse platforms in the Gulf of Mexico. Valaris will also drill two wells for PETRONAS off the coast of Suriname and extend its operations with BP in Egypt under a $25 million contract. Meanwhile, ARO Drilling, a joint venture between Valaris and Aramco, obtained three-year extensions for five platforms in the Middle East.
Fugro has been awarded a contract by Cadeler to conduct underwater inspections at the 960-megawatt (MW) East Anglia TWO wind farm in the UK. Work will begin in early 2027 and will cover 64 sites where the turbine foundations will be installed. The company will use a remotely operated underwater vehicle (ROV) to inspect the foundations and collect data from the seabed to verify that the structures have been correctly positioned.
Fugro is also working with Cadeler on the Hornsea 3 wind farm, where it is involved in the installation of 197 foundations. There, it is using InclinoCam, a technology that allows for centimeter-level accuracy in measuring the tilt and alignment of the structures during installation. Meanwhile, East Anglia TWO will have the capacity to produce enough electricity to power approximately 950,000 homes.
Jadestone Energy has increased its oil and gas production to approximately 19,000 barrels of oil equivalent per day after reactivating four offshore fields off the coast of Western Australia. Operations resumed after repairing a subsea connection and reconnecting the Okha floating production unit . Nearly all of the wells are now operational, with the fields producing approximately 8,000 barrels of oil per day, of which about 2,700 barrels are Jadestone's production.
The company owns 33.33% of these fields, operated by Woodside Energy, and also has operations in other Asian countries. In Malaysia, its PenMal operations are producing more than expected, while the Akatara facility has been at 96% availability since April. In Vietnam, Jadestone is negotiating with partners to develop the Nam Du/U Minh gas project, with the intention of making a final investment decision before the end of 2026.
Maritime Developments (MDL) has completed a series of subsea works for Oceaneering International off the coast of Egypt in the Mediterranean Sea. The work focused on replacing a damaged submarine cable and installing a new pipeline to help restore production capacity at two oil fields. The company used specialized equipment aboard the vessel Energy Savanah for this purpose .
During the operations, MDL installed underwater connection systems and used equipment that allows for the controlled placement of cables and pipes on the seabed. The company also manufactured a special structure for handling one of the cable components and was responsible for preparing the equipment and coordinating the work from its base in Peterhead, Scotland. This project adds to other work that MDL has carried out for Oceaneering in previous years.